Most commercial kitchen exhaust projects do not fail on engineering. They fail on a clause nobody read in the first year of the lease, and by the time the caterer has priced the hood, the fan and the duct run, the landlord’s surveyor has already decided whether the project happens at all. In a multi-let building the consent file, not the fan curve, sets the programme and the final bill.
Why the lease stops more projects than the building code does
Everything the authorities publish is public: approved document ventilation, the fire safety order, the environmental health officer’s odour guidance, the statutory nuisance provisions that let a neighbour complain about your extract. A competent contractor can read all of it and design to it. The lease is different. It is a private contract, it varies building by building, and it usually gives the landlord a veto that has no appeal route.
That asymmetry has a practical consequence for anybody buying equipment. A planning refusal can be reworked and resubmitted. An abatement notice can be argued. A landlord’s refusal to consent simply means the wall does not get drilled, and every hour of design work spent on a rooftop discharge that was never permitted is an hour nobody pays for.
So before a specification is fixed, three questions need answering in writing: do you have the right to make this alteration at all, do you have the right to use the roof or the riser, and what exactly must be removed on the day you hand the keys back. The answers decide the architecture far more than the cooking load does.
The four lease clauses that decide the project
The alterations clause
Alteration clauses come in four shapes and they behave very differently. An absolute prohibition — no alteration of the demised premises without the landlord’s consent, such consent to be at the landlord’s absolute discretion — gives the tenant no legal lever; consent is a favour, not an entitlement. A qualified covenant — consent not to be unreasonably withheld — is the common commercial form, and in England and Wales the law implies a reasonableness test into a qualified covenant against alteration and improvement. A conditional clause spells out what the landlord may require before consent: licensed contractors, structural calculations, specified materials, working hours, a supervisee’s fee. The fourth shape is silence, which is worse than any of the others, because silence gets resolved by argument after the equipment has been ordered.
What the tenant should be asking for is a licence to alter rather than a letter of consent. A licence is a deed, it binds successors, and it records the scope drawings, the contractor’s insurances, the working hours, the fee, the reinstatement obligation and the sign-off procedure in one document. An email saying “no objection” has none of that protection and gets forgotten the moment the building changes hands or the managing agent changes employer.
The reasonableness test cuts both ways, which surprises tenants. A landlord who insists on a licensed ductwork contractor, a tested fire-stopping system, a structural engineer’s letter and a reinstatement schedule is usually being reasonable. A landlord who refuses any penetration on a building where other tenants already have risers and roof plant is on weaker ground, but proving it costs more than the duct.
Services, plant and common parts
Rooftop plant is frequently outside the demised premises. The roof is a common part, and a common part is not yours to occupy. Installing a fan and a discharge terminal there needs either an exclusive-use plant zone carved out by the licence or an express right to keep equipment on a defined area — plus, and this is the clause tenants forget, a right of access to service and replace it. A right to install without a right to maintain is a trap that matures in year three, when the fan needs a bearing and the landlord’s facilities team will not open the roof hatch for a contractor who is not on their approved list.
The same logic applies inside the building. A shared riser is common property with a capacity that was calculated for the tenants who existed when it was built. If your duct occupies the last spare 600 mm, the next tenant’s consent will be refused because of you, and the managing agent will remember who took the space.
Reinstatement and yielding up
The clause that costs the most money is rarely read until the end. Yielding up in good and substantial repair and condition, fair wear and tear excepted, together with the removal of all alterations and making good, converts a modest hood replacement into demolition, roofing, fire-stopping restoration and redecoration. Fair wear and tear does not cover an alteration; it covers the building getting older, not the building getting changed.
A grease duct is a particularly expensive thing to remove because it is threaded through a building. Pulling the duct out means opening ceilings, cutting the duct into sections that will fit through a service lift, capping and making good a roof penetration with a new membrane patch and a fresh guarantee, removing the isolator and its cable, restoring the fire-stopping at every compartment line, and repainting whatever was disturbed. None of that appears in an equipment quotation.
Insurance and the tenant’s improvements
Most commercial property policies require the insurer to be told about alterations and about hot works. Undeclared works can void cover for the very fire the duct was designed to survive. Two further points need checking: whether the extraction system is insured as a tenant’s improvement or as part of the landlord’s building, and whether the policy excludes damage arising from grease-laden ductwork. Several landlord policies do, and a fryer line with a marginal cleaning regime is exactly the risk they had in mind.
If the landlord’s premium rises because of the new cooking operation, the lease almost certainly lets that increase be recharged. That is an operating cost of the menu, not a one-off project cost, and it belongs in the business case next to the fan power.
Five approvals that are not the landlord’s
Landlord consent is necessary and never sufficient. A rooftop terminal or an external plant enclosure may need planning permission, and permitted development rights for plant are routinely removed in conservation areas, on listed buildings and in some office-to-residential converted blocks. A route through historic fabric needs listed building consent, which is a separate application with its own timetable and its own scrutiny of every bracket.
Building control is engaged on ventilation and on fire. The extract system is a relevant requirement under the building regulations, and the compartment penetration is where most kitchen projects acquire a problem: a grease-bearing duct crossing a fire-resisting wall or floor needs a tested protection system, and the tested systems for ducts, seals and dampers are separate families with separate evidence. It is worth knowing that NFPA 96 prohibits fire dampers in grease ducts outright, because a closed blade becomes a grease trap; UK practice more often relies on a fire-resisting duct or enclosure, or a damper listed for the duty, and the fire engineer — not the equipment supplier — owns that decision.
Environmental health sits outside the consent chain but can close the kitchen afterwards. Odour and noise from commercial extract are actionable as statutory nuisance, and the officer’s assessment will look at discharge height relative to neighbours’ windows, at whether grease is depositing on their sills and plant, and at the noise rating at the nearest sensitive facade. A terminal that satisfies the landlord’s surveyor and irritates the flat opposite is not a finished job.
Above the landlord there may be a freeholder or a head lessee whose consent is also required, and a managing agent who operates a separate works licence with its own insurance minimums and permit-to-work system. And before any intrusive work, the building’s asbestos register needs reading: the duty to manage under the Control of Asbestos Regulations 2012 requires a refurbishment and demolition survey before ceilings, risers or roof decks are opened, and a licensed contractor if the material is friable.
Roof rights: what to ask for, and how to word it
A roof application is much easier to approve when it is specific. Vague requests get deferred; dimensioned requests get surveyed. The list below is the working content of a plant-zone schedule that a surveyor can actually assess.
Define an exclusive plant zone with a dimensioned drawing, including maintenance clearance — allow roughly a metre of working space around fans and access doors, plus the withdrawal space needed to lift a fan or an ESP cell out of its housing without dismantling the frame. State the imposed load and provide a structural engineer’s calculation for the plant, the duct supports, snow and wind uplift. Give the penetration schedule: how many cores, what diameter, where, and by what method, because percussive drilling is unacceptable in post-tensioned slabs and in some heritage soffits.
Weatherproofing needs a named system, an approved installer and a guarantee of ten to twenty years, with the guarantee assigned to the landlord rather than to the tenant who will eventually leave. Add a bonding connection to the lightning protection system, a condensate or grease-drain route, a lockable and labelled isolator at a location the landlord’s engineer can reach, and a safe access route for future cleaning that does not rely on the tenant’s own ladder.
Two technical numbers do most of the persuading. Keep discharge terminals at least a metre above roof level and at least three metres from any opening, intake or adjacent plant, so recirculation and nuisance complaints are designed out rather than argued later. And commit to a noise limit at the nearest sensitive facade, assessed to BS 4142:2014+A1:2019: a rating level within about 10 dB of the background is generally not significant, while a rating 10 dB above background is a significant adverse impact, and a tonal fan adds a penalty on top. A written commitment to the lower figure is worth more to the landlord than any brochure.
Routing through a shared building: risers, compartments and access
Measure the riser before designing the duct, not after. A 500 mm diameter grease duct needs roughly 600 mm of clear width once insulation, flanges and access doors are counted, and a shared riser that looked generous on a photograph is usually full of other people’s services, cabling trays and a legacy sprinkler main.
Every compartment penetration needs a tested fire-stopping detail with the certificate and the installer’s competency record attached to the consent file. Access for cleaning needs designing in at the same stage: horizontal duct runs need access doors at intervals and at every change of direction, sized for the cleaner’s tools, and the deposit limits that the cleaning standard works to — an average of around 200 micrometres with no single reading above 500 micrometres — are only achievable if the duct can be reached. Ductwork for grease service is built to a different standard from general ventilation ductwork: continuously welded or flanged with gaskets, no screw penetrations through the lower surface, and a fall towards a drainage point rather than a series of low spots that collect fat.
All of this has a consent angle. The landlord’s surveyor will ask who certifies the fire-stopping, who cleans the duct and how often, and what happens if the tenant’s contractor disappears. A named maintenance regime with a frequency and a record format answers all three at once.
The consent timetable: what actually takes the time
Programmes slip on consent, not on fabrication. A realistic sequence for a ducted route in an occupied multi-let building looks like this. A pre-application conversation with the managing agent and a site survey: one to two weeks. A formal licence application with drawings, method statement, risk assessment, insurance certificates and a plant-zone schedule: two weeks to be acknowledged. The landlord’s surveyor and structural engineer reviewing it: two to six weeks, and this is the step that absorbs most of the delay. Legal negotiation of the licence, usually overlapping the technical review: two to four weeks. Planning, if the terminal or enclosure needs it: eight weeks to determination in a straightforward case, longer where a heritage or design objection appears. Building control full plans: five weeks statutory determination, two to three weeks in practice.
In parallel, the asbestos survey takes one to two weeks and must precede any intrusive work; fabrication takes four to eight weeks from approved drawings; installation of a moderate duct run takes three to ten working days; commissioning and a witnessed test take one to two days. Add them honestly and a ducted project is a twelve to twenty week exercise from decision to a working kitchen, of which perhaps two weeks is the equipment itself.
This is the single most useful number to carry into a lease negotiation or a fit-out programme. A route that needs no penetration is not faster because the equipment is simpler; it is faster because six of those steps disappear.
What the surveyor will test before signing off
Landlord’s engineers and independent commissioning engineers ask the same questions, and having the answers pre-calculated shortens the review. Take a heavy cookline of 2.8 metres at the upper sizing rate of 2,400 cubic metres per hour per metre: 6,720 cubic metres per hour, rounded to 7,000, which is 1.94 cubic metres per second. In a 500 mm duct that is about 9.9 metres per second; in a 560 mm duct, about 7.9 metres per second. Both are comfortably above the minimum transport velocity needed to keep grease moving rather than settling, which is why the smaller duct is not automatically the cheaper answer — it is the one that needs cleaning more often.
The pressure budget follows the same logic. Canopy and filter entry around 40 Pa, a high-efficiency grease stage at 120 to 180 Pa when loaded, 25 metres of duct at 1.5 to 2.5 Pa per metre for 40 to 60 Pa, three bends at about 30 Pa each, a discharge terminal at 60 Pa and a non-return flap at 40 Pa, which lands between roughly 490 and 590 Pa before system effect. Add 10 to 15 per cent and specify a fan at 650 to 700 Pa. Shaft power then comes out at about 2.2 kW using a fan efficiency near 0.62, so a 3 kW IE3 motor is the honest selection — and it is the number the landlord needs for the electrical capacity and the noise calculation.
At commissioning, expect airflow within plus or minus 10 per cent of design and static pressure within plus or minus 5 per cent, measured on a traverse at a suitable plane and recorded on a nine-point grid at the hood face. Face velocity at the canopy opening should sit between 0.25 and 0.5 metres per second for light duty and 0.4 to 0.6 for heavy duty; a number below that range is the most common reason a compliant installation still leaves smoke in the room. Vibration isolation and flexible connectors matter more in a shared building than in a detached one, because structure-borne noise travels through the frame and arrives in somebody else’s ceiling.
Where odour is the sensitive issue, expect olfactometry to EN 13725 and a carbon contact time rather than a carbon weight. At 7,000 cubic metres per hour, a 0.4 second contact time means a bed of roughly 0.78 cubic metres, which at a typical bulk density is in the region of 360 kilograms of carbon — an annual consumable at any real operating hours, and a line item the landlord will want scheduled rather than promised.
Making good: the clause that outlives the equipment
Reinstatement is where a well-priced project turns expensive, and it is negotiable — but only before consent is granted. Four things belong in the licence. An itemised reinstatement schedule, so both sides know what removal means rather than discovering it at dilapidations. A cap on the liability, tied to the schedule rather than to the landlord’s discretion. A right to leave plant in place if the incoming occupier wants it, which costs nothing to grant and saves a demolition. And an agreed schedule of condition with dated photographs of the roof, the ceiling and the riser before any work starts, because a landlord’s dilapidations claim is only as good as the evidence of the original state, and that evidence is easier to agree at the start than to dispute at the end.
Two traps are worth naming. The first is assuming that removal is unnecessary because the next tenant will want the extraction. A landlord can claim the cost of removal even where the plant is likely to stay, and arguments about betterment are slow and uncertain. The second is treating an informal sign-off as a discharge of the obligation: a facilities manager’s email is not a variation of a deed, and the obligation to yield up runs to the end of the term regardless of who approved the installation.
Twelve documents worth assembling once
Consent applications are slow when they arrive in pieces. A single pack containing the following shortens every subsequent conversation and can be reused for the building control submission and the insurer: general arrangement and roof plan drawings; the plant-zone schedule with dimensions and loads; the structural engineer’s calculation letter; the method statement and risk assessment; contractor’s public liability and all-risks certificates; the fire-stopping system specification with the installer’s competency record; the ductwork specification and cleanliness regime; a noise assessment to the relevant standard; an odour assessment where sensitive receptors exist; the cleaning and maintenance schedule with frequencies; the commissioning specification with tolerances; and the reinstatement schedule with the schedule of condition photographs.
Twelve documents, assembled once, answer perhaps eighty per cent of the questions a surveyor, an inspector and an insurer will ask over the life of the installation.
When consent is refused, or simply too slow
Refusal is not the end of the project; it is a prompt to change the architecture. There are four routes, and they carry very different consent burdens.
A full ducted run to a roof terminal is the heaviest: roof rights, structural evidence, compartment protection, planning risk, noise and odour assessment, and a reinstatement obligation that involves roofing. Where the building genuinely supports it and the cooking load is high, it remains the right answer, and the ducted electrostatic precipitator line plus a matched centrifugal fan is the conventional pairing for that high-volume end of the market, sized on the transport velocity and pressure budget above rather than on a rule of thumb.
A recirculating ductless hood removes the penetration, and with it most of the argument. There is no roof right to negotiate, no compartment to protect, no terminal to assess for odour at a neighbour’s window, and the reinstatement obligation shrinks to unbolting a unit and making good a fixing. What remains is equipment consent, a dedicated circuit, and a maintenance regime for the filters and the odour stage. The engineering conditions do not disappear: capture at the canopy face still has to reach 0.25 to 0.5 metres per second, the heat and moisture stay in the room and have to be handled by make-up air and cooling, and the odour stage has a finite carbon life that needs scheduling. A ductless system is not an exemption from environmental health; it is a different compliance route that has to be documented just as carefully. For light-fume lines — griddles, ovens, light wok work — a compact recirculating hood from the ductless range hood range will carry the load; for charcoal, tandoor and high-volume frying the heavier ND-series is the appropriate selection, and where the terminal sits close to housing an odour tower stage is added rather than assumed. The N-series covers the light-fume end of the same decision.
A split arrangement sits between the two. A shallow canopy captures over the cookline, a short duct drops to a floor-standing cabinet roughly 520 mm wide in a back-of-house recess, and there is no vertical component above the hood — which is what makes the arrangement work at 2.4 metre ceilings and in buildings where the roof is simply not available. The consent burden is equipment plus a circuit and a condensate route, with none of the roof rights a terminal would need.
And where the cookline is not fixed at all — a market pitch, a terrace, an event, front-of-house live cooking — the ventless catering cart range removes the question entirely, because there is no builder’s work and nothing to reinstate beyond a floor to clean.
None of these routes is a way around the lease. Each is a way of making the lease easy to say yes to. The practical rule at selection stage is to price the consent envelope before pricing the equipment: decide how much builder’s work you are prepared to undo at the end of the term, then choose the architecture that fits inside that. A hood that needs a roof penetration is a ten-year commitment; a hood that needs a socket is a decision you can reverse on a Tuesday. Souniny builds all four routes for that reason, and the selection conversation is usually about the building rather than about the cooking.