Kitchen Exhaust Handover Pack: As-Builts, Registers and Sign-Offs

What belongs in a kitchen exhaust handover pack: as-built duct drawings with hatch positions, commissioning records with measured airflow, duct cleanliness class, the fire file, O&M manual language, spare parts and a serial-level warranty register - and the contract clauses that make the pack actually arrive.

Kitchen Exhaust Handover Pack: As-Builts, Registers and Sign-Offs

Handover is the last moment in a kitchen exhaust project when every party still holds a lever. The fan runs, the hood draws, most of the invoice is paid and a retention sits somewhere in escrow. What decides the remainder is rarely the equipment itself. It is whether the file behind the equipment can be read by somebody who was never on site, two years later, on the morning a fire officer or an insurance surveyor walks in with a clipboard.

Four readers, and none of them is the chef

A handover pack is not written for the person who signed the purchase order. It is written for four audiences who arrive at different times and ask different questions. The insurer wants evidence that the grease path was clean at acceptance and has been cleaned since. The fire authority or building control officer wants evidence that the duct route, its clearances and its penetrations were built as approved. The warranty administrator wants evidence that the system was commissioned to its design figures, because a claim on a seized bearing is hard to defend when nobody can show the fan was ever running at the right speed. The fourth reader is the one buyers forget: whoever inherits the site — a new tenant, a new maintenance contractor, or a purchaser doing due diligence on a building sale.

Each of those four reads a different document first, and each of them can stop something. A missing as-built drawing stops a cleaning contractor from finding the access hatch. A missing commissioning record stops a warranty claim. A missing penetration photograph stops an occupancy sign-off. The pack is therefore not paperwork that trails behind the project; it is the instrument that converts a working installation into a defensible asset.

Document 1 — as-builts, not shop drawings

The most common substitution in a closeout pack is a shop drawing relabelled as an as-built. They are not the same object. A shop drawing states what was intended: the duct was designed to run at a given size along a given route. An as-built states what exists, including the two extra offsets added on site to clear a sprinkler main, the reduced section behind the riser, and the hatch that ended up on the opposite face because the wall was not where the drawing said it was.

A usable as-built for a kitchen exhaust system carries five things. First, the dimensioned duct route measured from a fixed datum — a grid line or a structural column — not from another duct. Second, every access panel and cleaning hatch with its size and opening direction; a clear opening below roughly 300 mm is not a cleaning hatch, it is a viewing slot. Third, the fan position, its mass, and the supporting steel. Fourth, the isolator location and the containment route, marked in a place a cleaner will never confuse with a light switch. Fifth, the test points: where a pitot traverse or a vane reading can actually be taken without dismantling a section.

The practical test of an as-built is simple. Hand it to a cleaning contractor who has never seen the building and ask them to locate every hatch. If they have to guess, the drawing has failed, and the failure will surface as a cut hole in a duct that was not designed for one.

This matters more than it used to because duct cleanliness regimes have hardened. EN 15780 and the UK’s TR19 Grease both condition a valid cleaning certificate on access being available at the required intervals; a system that cannot be reached cannot be certified, and an uncertified system is an argument the owner loses in front of an insurer.

Document 2 — a commissioning record with numbers in it

The weakest sentence in most handover packs is “system tested and commissioned”. It carries no information. A commissioning record earns its place only when it states measured quantities, the instrument used, and the tolerance against design. For a kitchen extract system the minimum set is: airflow at each hood in cubic metres per hour, capture velocity at the hood face in metres per second, static pressure at the fan inlet, fan speed and absorbed current per phase, motor overload setting, make-up air volume, room pressure differential, clean pressure drop across each filtration stage, and sound pressure level both at the hood and at the nearest sensitive boundary.

The method has to be named, because methods disagree. A pitot traverse to ISO 3966 needs a measurement plane with roughly five duct diameters of straight run upstream and two downstream of the last disturbance; where that does not exist, a hood-face grid of at least nine points with a calibrated vane is more honest than a single centre-line reading multiplied by area. Fan performance, where no straight run exists at all, can be inferred from the fan curve to ISO 5801 using speed and power, provided the curve is supplied with the unit and the impeller is clean at the time of test.

Typical acceptance tolerances in ventilation commissioning are plus or minus ten per cent on airflow and five per cent on pressure. Those two numbers should tell a coherent story. An airflow shortfall of eight per cent paired with a static pressure shortfall of twenty per cent almost never means the fan is too small; the fan affinity laws say flow varies with speed and pressure with the square of speed, so that pattern points at a throttled damper, a collapsed flexible connector, or a filter left in its transport wrap.

Take a workable example. A three-metre heavy-load cookline designed at 2,500 cubic metres per hour per metre of hood lands at 7,500 cubic metres per hour, or 2.08 cubic metres per second. A 560 mm duct carries that at about 8.5 metres per second, inside the 7.6 to 10 metres per second band that keeps grease entrained rather than depositing. A pressure budget of 40 Pa across the hood filters, 30 Pa of straight duct, 60 Pa of fittings, 120 Pa across a precipitator stage, 180 Pa across the carbon stage, 40 Pa at discharge and 60 Pa across the balancing damper totals roughly 530 Pa; adding fifteen per cent margin gives 610 Pa, so the fan is selected at 700 Pa. Shaft power then lands near 2.1 kW at 0.62 efficiency, and a 3 kW motor covers it with reserve for a loaded filter. Every one of those numbers belongs in the record, because each is a future argument the owner will otherwise lose.

Document 3 — cleanliness at handover, stated as a class

Construction dust, swarf and wrapping tape left inside a duct become the first year’s fire load and the first year’s bearing failure. Cleanliness at handover should therefore be certified, not asserted. EN 15780 defines ductwork cleanliness classes with deposit thresholds, and its sampling annex works on a gravimetric basis: mass of deposit per square metre, converted to an equivalent film thickness, with commonly cited thresholds around 200 micrometres as an average, above which cleaning is required, and above 500 micrometres as an urgent condition.

The certificate should state the date, the sampling points by asset ID, the method, the mass recorded, and the class achieved. In the UK market the equivalent document is a post-construction clean certificate issued against TR19 Grease. In either case there is a sequencing trap worth naming: the duct must be cleaned after the final connections and after the ceiling or wall finishes are complete, not before. A certificate dated three weeks before the last penetration was sealed certifies nothing.

Document 4 — the fire file

Grease duct fire safety is the part of the pack that gets audited hardest, because it is the part that kills people. Six items belong in it. Penetration seals, each recorded with product, rating, installer and a photograph before the enclosure closed. Clearance to combustible construction, measured and photographed at every tight point; the familiar figure is 457 mm, or protection to an equivalent standard where that clearance cannot be held. The suppression system, with its cylinder location, manual pull station, fuel and power shut-off interlock, and a witnessed test certificate. The damper schedule, noting that grease ducts are generally not fitted with fire dampers in the canopy branch, and where dampers do exist, their positions and access. The isolator, lockable, labelled, and sited clear of the cooking zone. And any duct temperature or thermal detection, with its alarm matrix.

Where the jurisdiction has a periodic servicing regime for fire safety systems, the handover file should also carry the first scheduled service date, because the obligation transfers to the owner the day the kitchen opens and it is the owner who is fined when it lapses.

Document 5 — an O&M manual in the language of the person who will use it

An operations and maintenance manual written only in the manufacturer’s language is a compliance defect in a growing number of markets. Occupancy files in several European jurisdictions now expect installation and maintenance instructions in the national language, and an inspector who cannot read the maintenance schedule will treat it as absent. The manual should therefore be issued in the local language, with the maintenance schedule as a standalone one-page table that can be laminated and hung on the wall beside the hood.

The schedule itself should be interval-based and load-based, not vague. Daily wipe-down of the hood canopy and grease cups. Weekly washing of the primary filters, more often in a fryer-heavy kitchen. Monthly check of the differential pressure across each stage against its clean baseline. Quarterly deep clean of the precipitator cells, with the interval shortened where the pressure trend says so. Duct cleaning at intervals set by load class — commonly twelve months for light-duty cooking, six for medium, three for heavy, and one to three for solid fuel, always subject to the authority having jurisdiction and the insurer. Each line needs a signature column, because a filled log book is accepted where a verbal assurance is not.

Document 6 — spare parts, wear items and the warranty boundary

The parts list is the document that determines how long the kitchen is closed after the first failure. It should carry part numbers, photographs, quantities on site, and a lead time for each item, because a fan motor sourced from Asia by sea is a five to eight week event and by air a matter of days. A defensible critical spares holding for a single heavy extraction system is one set of filter media, one set of gaskets and seals, one differential pressure switch, two ceramic insulators, and either a spare motor or at minimum its bearings and starting capacitor.

The same page should state the wear-item boundary in plain words. A twelve-month whole-unit warranty that excludes consumables is normal; discovering at claim time that collector plates, gaskets, filter media and insulators are classed as consumables is not. The boundary belongs in the handover file, on the page the maintenance technician will actually open.

Document 7 — a warranty register at serial level

Warranty is administered per asset, not per project. The register therefore needs one row per item: asset ID, model, serial number, install date, commissioning date, warranty start date, cover duration by component, and the end of the defects liability period. The recurring trap is the start date. Many purchase orders default warranty to the delivery date; on a site that sits fit-out for six months before opening, that quietly burns half the cover before the first service call. Commissioning date, or handover date, is the defensible trigger, and it is worth one line in the contract.

Document 8 — training and authorised persons

Who may open the electrical enclosure, who may reset an interlock, who may clean a cell — three questions, three names, three dates. Training records feel like the softest part of a closeout pack until an incident investigation asks who authorised the intervention. One page, signed, with the competence evidence attached, closes the question permanently.

The living document: an equipment register that survives ten years

Everything above is a snapshot of one day. The register is the part that keeps working. Its fields are unglamorous and each one earns its keep: asset ID, site, room or zone, model, serial, hood length, design airflow, filter size, load class, cleaning interval, last clean date, next due date, measured airflow at commissioning and at every subsequent service, and the clean pressure drop baseline for each filtration stage.

The value is in the trend, not the snapshot. An airflow that has fallen fifteen per cent across three services is a partially blocked duct or a saturated stage, and it is visible months before a customer complains about odor in the dining room or a cook complains about heat. A pressure drop that has doubled against baseline is a filter that needed washing two weeks ago. Site managers who keep the trend catch both events early; site managers who keep only the last certificate catch neither.

Across multiple sites the register becomes the only reliable basis for budgeting and for standardizing specification. Asset IDs must be issued so they survive a refurbishment, printed on a durable label at the canopy edge and repeated inside the electrical enclosure, because a register that depends on a memory of which unit was which is a register that dies with the staff turnover.

What a missing document actually costs

Document Who asks for it What happens without it
As-built duct route with hatch positions Cleaning contractor, insurer Access improvised on site; unauthorised penetration; cleaning certificate refused
Commissioning record with measured airflow Warranty administrator Performance claims become arguable; defects period disputes drag on
Duct cleanliness certificate and class Fire officer, insurer Occupancy delayed; re-clean at the owner’s expense
Penetration seal photographs Building control Sign-off refused until the enclosure is opened and re-inspected
Suppression test certificate Fire authority Kitchen cannot open for cooking
O&M manual in the local language Occupancy inspector File judged incomplete; re-issue and re-inspection cycle
Spare parts list with lead times Maintenance, operations Weeks of closure over a low-value component
Warranty register at serial level Finance, asset management Cover lapses silently; nobody notices until a failure
Training and authorised persons record Health and safety, insurer Liability lands on the operator after an unauthorised intervention
Measured noise level at the boundary Planning authority Enforcement action against a plant item that was never tested

Contract mechanics that make the pack arrive

A handover pack that is requested after practical completion arrives late, incomplete, and in a format nobody can search. The fix is mechanical and belongs in the contract, not in a reminder email. Three clauses do most of the work. First, list the deliverables as a schedule to the contract, each with a named format, a language and a revision convention, so “documentation” stops being an adjective. Second, make the pack a condition precedent to the final payment and to the release of retention, with retention commonly split between practical completion and the end of the defects period. Third, set a document window, typically fourteen days from commissioning, with a small document holdback released only on acceptance of the pack.

Two definitions prevent most of the arguments. Define as-built as a record of installed condition measured on site, and state that a marked-up shop drawing will not be accepted in its place. Define the commissioning record as measured data with instrument identification, and state that a design schedule returned unaltered will be rejected. Both definitions cost two lines and save a month.

Six failure modes worth checking for before you sign

One: the PDF pile — six hundred pages with no index, which nobody will ever open again. Two: the shop drawing passed off as an as-built, usually detectable because the dimensions do not close against the room. Three: commissioning figures copied from the design schedule, detectable because every value is a round number. Four: duct cleaned before the final connections, detectable from the certificate date against the penetration seal date. Five: an O&M manual in a language the inspecting authority does not read. Six: a register maintained by the installer rather than the operator, which stops being updated the week the installer leaves site.

Digital conventions solve the first and the sixth at almost no cost. One folder per asset, PDF/A for anything that must remain readable in a decade, drawings issued as both native and PDF, filenames built from the asset ID and revision, a QR label on the canopy that resolves to the folder, and a points list for any equipment connected to a building management system, with the alarm matrix spelled out rather than implied.

How the architecture changes the size of the file

The document burden is not the same for every system, and buyers who understand this can trade paperwork against plant. Where the building has a viable riser and the cooking load is heavy, a ducted stack with a precipitator stage and a Centrifugal Fan gives the most codified numbers in the industry — but it also demands the full fire file, the duct cleanliness regime, the access panel survey and the suppression interface. That is four of the eight documents above existing only because the grease leaves the room.

Where the roof cannot be penetrated, or the riser does not exist, a ductless recirculating hood with a multi-stage electrostatic stage and a carbon stage removes most of that burden at a stroke: no grease duct register, no penetration seals, no damper schedule. What replaces it is a consumable register and a pressure drop log, which is a far lighter thing to maintain. The same logic scales down through a floor-standing cabinet unit where clear height is short, and through mobile catering carts where the register simply travels with the asset and every unit needs its own serial.

That is the trade in its honest form. A ducted system concentrates the compliance risk in the fabric of the building and asks for a heavy file. A recirculating system concentrates it in filter maintenance and asks for a light file plus discipline. Neither is free; the mistake is choosing one and then managing it as if it were the other.

For buyers comparing offers, the useful move is to send the same eight-document schedule with the enquiry and ask each bidder to state which items they issue, which the installer issues, and which fall to the client. The answers arrive before the price comparison, and they usually explain most of the price difference. Between a ducted stack and the ductless range hood family, the gap in closeout effort is often larger than the gap in equipment. Where a full duct run is possible and the volume justifies it, the ducted ESP filter range covers that high-volume end; where the site is a market stall, a pop-up or a front-of-house live cooking position, the mobile catering cart range moves the whole compliance story onto a single serial-numbered asset.

Found this article helpful? Share it with your colleagues.

SOUNINY Application Engineering Team
SOUNINY Application Engineering Team
Commercial Kitchen Ventilation Specialists

A multidisciplinary team of application engineers and kitchen-ventilation specialists at Shenzhen Shuangni Environmental Technology Co., Ltd. (SOUNINY). We design, test and deploy grease, smoke and odor-control systems for restaurants, hotels, food factories and ghost kitchens across 30+ countries, and author the technical guidance published on this site.

← Back to News Request a Solution
FAQ

Frequently Asked Questions

What must a kitchen exhaust handover pack contain?
Eight items cover most inspections: as-built duct drawings dimensioned from a fixed datum with every access hatch located, a commissioning record with measured airflow per hood and static pressure at the fan, a duct cleanliness certificate stating the achieved class, a fire file with penetration seals and clearance photographs, an O&M manual in the local language with an interval-based maintenance table, a spare parts list with lead times, a warranty register at serial level, and training records for authorised persons.
Why is a shop drawing not acceptable as an as-built?
A shop drawing records intent; an as-built records installed condition, including offsets added on site, reduced sections behind risers and hatches relocated because a wall was not where the drawing showed it. Cleaning contractors and fire officers work from the installed geometry, so a relabelled shop drawing sends them to the wrong place - which typically ends as an unauthorised cut in a duct that was never designed for one.
What airflow tolerance should commissioning be accepted against?
Plus or minus ten per cent of design airflow and five per cent on static pressure are the usual ventilation commissioning tolerances. The two figures should be read together: because flow varies with fan speed and pressure with its square, a small airflow shortfall with a large pressure shortfall points to a throttled damper or a blocked filter rather than an undersized fan.