The electrical order usually goes in three to four weeks before the hood arrives, placed by an electrician who has seen neither the fan curve nor the control panel drawing. That timing is where most extract “fan problems” are born: a three-phase fan that trips its breaker on every start, a purification unit that takes out a residual current device on wet mornings, an isolator on a roof nobody can reach safely. None of these are equipment faults. They are specification decisions taken too early, on too little information, and they surface later as call-outs in the middle of service.
Where Extract Electrical Failures Actually Come From
The same three mistakes recur across new-build and retrofit projects. They are worth naming before the design is fixed, because each is cheap to solve on paper and expensive to solve on a roof.
The breaker is chosen by what fits the enclosure, not by the starting current. A 3 kW three-phase motor draws roughly 5.9 A when running but six to eight times that for a fraction of a second at direct-on-line start. A breaker sized on the running current only will hold in warm weather and nuisance-trip in a cold kitchen, which is exactly when the staff report a “faulty fan”.
The protective device and the variable speed drive disagree. A drive with an EMC filter leaks current to earth by design. Put it behind an ordinary 30 mA residual current device and the site inherits a fault that appears when humidity rises and disappears when the technician arrives.
The scope of supply stops at the terminal box. Supplier ships a fan; installer assumed the control panel was included; the client assumed the interlock to the gas valve was somebody else’s drawing. Three parties, three assumptions, one kitchen that cannot be signed off.
A quick test of whether the electrical design exists: ask for motor full-load current, starting method, breaker type and cable size in writing. If the answer is a kW figure and a shrug, the design has not been done and the risk has simply moved to site.
The Arithmetic a Buyer Can Check in Five Minutes
Electrical arguments end quickly when both sides work from the same three numbers: full-load current, starting current and run length. All three can be derived from the motor nameplate, and all three belong in the quotation rather than in the installer’s head.
For a three-phase motor on a 400 V supply, full-load current is the shaft power divided by the product of root three, voltage, power factor and efficiency. A worked example: a system needing 7,500 m3/h at roughly 700 Pa absorbs about 2.35 kW at the shaft, so a 3 kW motor is selected. At a power factor of 0.85 and an efficiency of 0.87, the current is 3,000 divided by (1.732 x 400 x 0.85 x 0.87), which comes to about 5.9 A. That is the number to check against the nameplate, and the number the breaker must be selected from.
Starting current then follows from the starting method, and this is where quotations differ without saying so:
- Direct-on-line: six to eight times full-load current, so roughly 35 to 47 A for 0.1 to 0.3 seconds.
- Star-delta: two to three times, at the cost of a six-terminal motor and a transition step.
- Soft starter: three to four times, ramped over five to fifteen seconds.
- Variable speed drive: close to 1.1 to 1.2 times, at the cost of harmonic distortion and earth leakage.
A 10 A type C breaker trips magnetically between five and ten times its rating, so it clears a 47 A inrush comfortably while still protecting a 2.5 mm2 cable rated near 20 A when clipped. A type D device, tripping at ten to twenty times rating, is the fallback for a hard direct-on-line start. Both are defensible; what is not defensible is a device chosen without either calculation.
Cable size is then a voltage-drop question as much as a current question. A 2.5 mm2 copper three-core cable on a 25 m run at 5.9 A loses roughly 15 mV per ampere per metre, about 2.2 V, which is well under half a percent of 400 V and comfortably inside the five percent total drop allowed by IEC 60364-5-52 and the tighter three percent usually wanted on motor circuits. On a 60 m roof run the same cable is nearer 1.3 percent and still acceptable; it is the 4 mm2 upgrade on long runs that people forget, not the current rating.
Single-phase equipment follows the same logic with different numbers. A 1.5 kW motor on 230 V at a power factor of 0.9 and efficiency of 0.85 draws about 8.5 A, so it sits on a 16 A circuit with 2.5 mm2 cable once the run passes about 20 m. Small units offered with a factory plug are the ones most often extended on a domestic extension lead, which is a fire risk rather than a performance issue.
Five Lines That Must Be on the Electrical Drawing
An extract system drawing that does not carry these five items is not a design, it is a picture of a fan. Demand them before fabrication, because all five change the price if they are added later.
- Supply characteristics at the point of connection: voltage, number of phases, frequency, full-load current, starting method and the design ambient temperature used for the panel.
- Point of isolation: the exact position of the isolator for each motor, and whether it is local or at a remote panel.
- Cable specification and route: size, cores, insulation, whether screened, and the length assumed. Roof runs and risers are where the estimate and the invoice diverge.
- Control panel position and ingress protection: indoors in a dry plant room, or outdoors on a roof where the enclosure rating decides its service life.
- Interlock schedule: which device signals which action, in table form, with the device type and the terminal it lands on.
The interlock schedule is the line most often missing, and the one an authority or commissioning witness will ask for first. A single page listing device, signal, action and test method is enough; a paragraph of prose is not.
Isolators, Access and the Roof Nobody Wants to Visit
Isolation is a safety requirement and a maintenance cost at the same time. The practical rules that survive contact with real buildings are simple: the isolator must be lockable, it must be reachable by one person without a ladder, and it must be visible from the equipment it isolates so a technician can see that the circuit is dead rather than trusting a label.
On a roof, that combination is often impossible, which is why a remote isolator plus a local maintenance switch is the usual compromise. Either way, the position must be agreed while the cable route is still being drawn, not discovered by the electrician on the day. A roof isolator that requires a permit, a key and a second person to reach is an isolator that will not be used, and equipment that is never isolated is never properly cleaned.
Two further details decide whether the installation survives: an emergency stop at the kitchen exit for any system that can run unattended, and labelling in the language of the people who will operate the panel. A panel labelled in the manufacturer’s language is a panel that gets operated by trial and error. Where the kitchen is in a heritage or listed building, the isolator position also has to satisfy whatever the building consent allows, which is a planning constraint rather than an electrical one and is worth raising in the first design meeting.
Residual Current Devices, Drive Leakage and the Wet-Morning Trip
Earth leakage is the single most misunderstood part of kitchen extract electrics, because the two devices involved are protecting against different things and neither is at fault when they conflict.
A residual current device looks for current returning by the wrong path. A variable speed drive, by design, sends a small high-frequency current to earth through its filter. A 30 mA device is sensitive enough that several drives on one circuit, or one drive with a long screened motor cable, can approach the trip threshold on a humid day. The result is a trip that appears to be caused by the kitchen being washed down.
The engineering answer is to state the leakage current for each drive in the submittal, to keep screened motor cable short or use the manufacturer’s recommended cable, and to select the device type deliberately. Where local rules demand 30 mA protection, a type B device rated for smooth and pulsating residual current is the usual requirement for a three-phase drive; where 300 mA is permitted, that is the quieter choice. Either way, the leakage figure has to come from the drive manufacturer rather than from an assumption, because a filter option can multiply it.
High-voltage purification stages have their own version of the same problem. The cells draw milliamps at kilovolts, so the load is trivial, but the switched-mode supply in the cabinet is a leakage source of the same kind and the control circuit must not be borrowed from a lighting circuit. Sharing a circuit with lights is how a purification unit ends up switched off every night at closing time and reported as a failure the following morning.
Interlocks: The Safety Chain Nobody Tests
Interlocks are cheap devices carrying expensive consequences, and they are the part of an extract system most likely to be installed correctly and never tested again.
The chain usually includes a differential pressure switch proving airflow or filter condition, a duct temperature device, the fire suppression system’s discharge signal, a gas solenoid valve and, on purification equipment, a door switch that removes high voltage when a cell is accessed. The logic runs in one direction: prove airflow, then enable gas; lose airflow, close gas; detect discharge, close gas and record the event.
What happens to the fan on an alarm is a code question rather than an engineering preference, and answers differ between jurisdictions and between suppression standards. Some arrangements require the fan to stop so that a suppression agent is not pulled out of the hood; others require continued operation to remove smoke. The right move for a buyer is to have the decision recorded in the interlock schedule, agreed with the authority who will inspect it, and tested at commissioning with the result written into the handover file. A chain that has never been tested is a chain that will fail during the one event it exists for.
Annual testing belongs in the maintenance scope, with the same discipline as the suppression system itself: trip each device, confirm each action, record the date. Ten minutes of testing per device is the cheapest insurance in the building.
Phase Balance, Shared Risers and Sub-Metering
In a food hall, a mall unit or a shared kitchen building, the extract system rarely gets a supply of its own. It shares a distribution board with refrigeration, dishwash and lighting, and the way it is connected decides whether the building has a stable supply or a permanent complaint.
Two practical points. First, keep the fan and its control panel on a three-phase supply and distribute single-phase loads across phases, because a heavily unbalanced board gives uneven voltage, which shortens motor life and produces the humming that staff describe as “the fan is struggling”. A 400 V three-phase 16 A way is about 11 kVA of capacity, which is a useful figure when comparing what the landlord offers against what the equipment needs. Second, decide about sub-metering early. A meter on the extract circuit costs very little at fit-out and settles the argument about who pays for a fan that runs twelve hours a day; retrofitting one costs a shutdown.
Where the tenant pays for electricity but the landlord owns the riser, the meter also gives both parties a shared number to discuss when a fan is left running overnight. That is an operational conversation that is much easier with data than with opinions.
Derating for Heat, Humidity and Coastal Air
Equipment selected in a European catalogue and installed in a tropical rooftop plant room is being asked to work outside its assumptions. Three derating factors matter and all three should appear in the quotation.
Ambient temperature inside an enclosure is typically 10 to 15 K above outside air, so a panel rated for 40 C is being pushed at 35 C outdoor conditions. Breakers are calibrated at 30 C in many standards and lose capacity as temperature rises, which is why a device that is marginal on paper trips in service. A fan running continuously in a hot roof space also needs its motor insulation class and bearing grease specified for the duty, not for intermittent use.
Humidity drives condensation, and condensation inside a control panel is the most common cause of nuisance earth leakage. A anti-condensation heater or a breather drain costs a fraction of a service visit. Coastal sites add salt, so enclosure and fixings need a corrosion category suited to the location, and stainless fixings are not a luxury on a seafront roof.
The Twelve-Line Electrical Schedule to Demand Before Order
This is the page that turns a conversation into a comparable bid. Ask every supplier to fill it in, and the cheapest quote usually stops being the cheapest.
- Motor rating in kW and the full-load current from the nameplate.
- Supply voltage, phases and frequency assumed.
- Starting method offered, with the starting current multiple.
- Recommended breaker type, rating and curve.
- Recommended cable size and maximum run length.
- Isolator type, position and ingress protection.
- Control panel location, enclosure rating and dimensions.
- Leakage current for each drive or power supply, with the filter option stated.
- Interlock devices supplied, and those assumed to be by others.
- Spare ways and spare terminals left in the panel.
- Warranty terms for the controls, separate from the mechanical warranty.
- Commissioning support included: attendance days, and who signs the electrical test sheet.
Two of these lines do most of the work. Line nine exposes the scope gap that causes most site arguments, and line twelve exposes a supplier who intends to hand over a running fan without a test record.
Acceptance Measurements That Settle Arguments
Electrical acceptance is measurable, and a buyer with a clamp meter and a checklist can hold the line without an engineering degree. Record the readings, keep them with the handover pack, and the system has a baseline for every future service visit.
Running current should land between 0.85 and 1.05 times nameplate full-load current on each phase, with phase imbalance under five percent. Insulation resistance on the motor circuit should read at least one megohm at 500 V test voltage, and earth continuity should be confirmed at the motor frame and every metal enclosure. Phase rotation must be checked before the fan is run, because a centrifugal fan running backwards still moves air, just badly, and the symptom is reported as poor extraction rather than reversed wiring.
Then test what actually protects people: trip the airflow proving device and confirm the gas valve closes, open a cell access door and confirm high voltage drops, press the emergency stop and confirm the fan stops. A thermographic check after two hours of running shows a loose terminal before it becomes a fire, and takes less time than writing the report.
Six Clauses That Keep the Electrical Scope Closed
Electrical arguments are scope arguments wearing technical clothing. Six clauses close most of the gaps.
Define the point of connection precisely, including who provides the final circuit and the isolator. Require the electrical schedule as a submittal, with the manufacturer’s data rather than the sales description. State the interlock schedule as a deliverable and make commissioning of each interlock a condition of practical completion. Fix the enclosure ratings by location, not by preference. Require the test sheet, signed, as part of the handover file. And make spare capacity explicit: two spare ways and ten percent spare terminals is a sentence that costs nothing now and saves a shutdown later.
How the Architecture Changes the Electrical Ask
The electrical scope follows the architecture, which is why the choice should be made before the distribution board is ordered rather than after.
A ducted installation carries the heaviest electrical package: a three-phase motor, a drive or starter, a control panel, and the full interlock chain to gas and suppression. If the building can accept a duct run, the ducted electrostatic precipitator range covers that high-volume end, and the electrical design should be priced with it from the start.
A ductless installation collapses most of that package into one unit. A light-fume all-in-one hood draws from a single-phase circuit, needs no interlock to a remote fan because there is no remote fan, and the only coordination left is the circuit capacity and the condensate or grease handling. That simplification is the main reason ductless systems suit leased units where the tenant controls nothing beyond the socket: the ductless hood family and its odour stage do the work of a duct, a fan and a panel in one footprint.
A split cabinet layout sits between the two: the canopy is passive, the cabinet carries the electrical load, and there are now two supplies to coordinate instead of one. Mobile units are simpler again, and the electrical question becomes generator capacity rather than breaker selection, because a cart with a single-phase load and a domestic generator is a sizing exercise in kVA with a margin for starting. For event work, the ventless catering cart range is normally chosen precisely because it removes the three-phase negotiation with a venue.
The general principle: every architectural decision that removes a remote fan also removes a cable run, a starter, an interlock and a failure mode. Electrical simplicity is a design output, not a procurement afterthought.
Five Failure Modes That Repeat
Most of what goes wrong electrically has already gone wrong on another project. These five are worth checking on any bid.
A breaker matched to the cable but not to the inrush, producing a trip on start that is diagnosed as a motor fault. A drive behind a 30 mA device that trips in humid weather, resolved by removing the protection rather than by changing its type. An isolator installed where nobody can reach it, so the equipment is never isolated and cleaning is done live. Controls fed from the lighting circuit, so the purification stage switches off with the lights. And a commissioning sheet that records the fan running without recording current, rotation or interlock tests, which leaves nothing to compare against when performance is questioned six months later.
The pattern behind all five is the same: the electrical design was treated as a site activity rather than a design activity. A buyer who asks for the five-line drawing, the twelve-line schedule and the signed test sheet is asking for very little paper, and gets a system that can be maintained by people who did not install it.
Related solutions: if you are working through a similar decision, the Solutions index collects every note by venue, cuisine, market regulation and project stage.